Wednesday, February 29, 2012
Awkward Teenage Phase
The house is experimenting with striped siding while the insulation goes in. Things should look better when all the boards are painted.
Monday, February 27, 2012
Saturday, February 25, 2012
February 21st - Electrical and Plumbing Mostly Done
Wednesday, February 15, 2012
Roof's On, Windows are In, HVAC Started...
...and the gas line is in and the plumber has started. The electrician comes for a review tomorrow afternoon.
Partial Roof on a Snowy Day
The roofers got the northeast side of the main pitch and 2/3 of the southwest side of the main pitch done Friday afternoon February 10th prior to the snow day February 11th.
Moonset over Hayesville February 7th 2012, 6:30 a.m.
Tuesday, February 7, 2012
Saturday, February 4, 2012